How to Build a Stud Wall

Last updated: September 2026

A timber stud wall is the quickest way to divide a room, create a walk-in wardrobe, or box in an awkward space. It's a very achievable DIY job if you plan it carefully.

What a stud wall is made of

  • Sole plate: a length of timber fixed to the floor.
  • Head plate: a matching length fixed to the ceiling joists.
  • Studs: vertical timbers between the two plates, usually at 400mm centres (600mm is sometimes used, but 400mm gives a stiffer wall and suits 1,200mm-wide plasterboard).
  • Noggins: short horizontal timbers between the studs, usually one row at mid-height, to stiffen the wall and give fixing points.
  • Plasterboard: usually 12.5mm, 2,400 × 1,200mm sheets, on one or both sides.

The most common timber is CLS (planed, rounded-edge studwork timber), in 38 × 63mm or 38 × 89mm. Use the deeper size for taller walls, doorways, or where you want thicker insulation.

How much will you need?

For a wall 3.6m long and 2.4m high with studs at 400mm centres:

  • Studs: 10 (3.6 ÷ 0.4 = 9, plus one for the end)
  • Plates: 7.2m (floor and ceiling)
  • Noggins: about 3.6m for one row
  • Plasterboard: 3.6 × 2.4 × 2 sides = 17.28m², which is 6 sheets, or 7 with 10% extra
  • Screws: about 30 per board

Add two extra studs and a head for each doorway. The Stud Wall Calculator works out timber lengths, plasterboard, screws and insulation for your wall.

Step-by-step

  • Check for pipes and cables in the floor, ceiling and walls with a detector before fixing anything.
  • Mark the line on the floor, then transfer it to the ceiling with a plumb bob or laser level.
  • Fix the head plate to the ceiling joists. If the joists run parallel to your wall, fit noggins between them to fix into.
  • Fix the sole plate to the floor – screws into timber floors, or plugs and screws into concrete. Leave a gap for any doorway.
  • Fix the end studs to the existing walls.
  • Mark and fit the studs at 400mm centres. Cut each one to fit snugly between the plates, and fix by skew-nailing or screwing.
  • Frame the doorway with a stud each side and a head timber at door height (allow for the door lining).
  • Fit noggins between the studs.
  • Run any cables before boarding, and get electrical work done by a qualified electrician.
  • Insulate. Acoustic mineral wool between the studs makes a big difference to noise between rooms.
  • Board the wall. Fix plasterboard with drywall screws about every 150–300mm, staggering the joints on each side.
  • Tape and finish. Tape and fill the joints, or have the wall skimmed, then mist-coat and paint.

Do I need Building Regulations approval?

A simple non-loadbearing stud wall in an existing home often doesn't need approval. It can, though, if it affects fire escape routes (for example, creating a room you can only get out of through another room, or in a loft conversion), affects ventilation (such as bathrooms or rooms without windows), or forms part of a bigger project. If in doubt, ask your local council's building control team before you start.

Frequently asked questions

What size timber for a stud wall?

38 × 63mm CLS for most walls, or 38 × 89mm for taller walls, doorways and extra insulation.

Should studs be at 400mm or 600mm centres?

400mm is stiffer and standard for 12.5mm plasterboard. 600mm uses less timber but the wall feels less solid.

Do I need to insulate a stud wall?

It's not essential for internal walls, but acoustic insulation makes a big difference to sound between rooms.

Can a stud wall hold a TV or shelves?

Yes, if you fix into the studs or noggins, or use cavity fixings rated for the weight. Plan extra noggins where heavy items will go.

Use the calculator